EPC Contracts in the Tanzania and East Africa Construction Sector

  • Market Insight 02 April 2025 02 April 2025
  • Africa

  • Corporate & Advisory - Regulatory Risk

  • Projects & Construction

The construction industry plays a vital role in the economic development of Tanzania and East Africa. The industry is experiencing rapid growth, driven by government initiatives and foreign investment. It is essential for investors to understand the mechanics of construction projects, the key stakeholders, the agreements involved, and how to navigate potential risks. Effective risk allocation under EPC Contracts is critical to ensuring bankability, stability, and sustainable investment in the sector.

In this article, we identify some of the key points to consider when negotiating and implementing EPC Contracts in Tanzania and East Africa. We also examine some of the necessary consents and permits in Tanzania, along with specific jurisdictional risks. A clear understanding of these factors will help facilitate the successful negotiation and implementation of projects.

Structure of a Typical Construction Public Private Partnership (PPP) Project

EPC Contracts tend to be most appropriate on major infrastructure projects. In recent years, several major projects in Tanzania have been procured as PPPs. Investment in PPP projects is growing significantly in Tanzania, supported by the passing of new legislation. With that comes increased opportunity for global contractors. 

For context, we summarise below a typical PPP project structure. 

new-graph.jpg

A typical PPP Project involves multiple stakeholders, with EPC Contractors appointed by the Project Company to undertake the design and construction of the project. 

Tanzanian EPC contracts for large scale projects commonly follow the FIDIC standard forms, with the 1999 Yellow Book and the 2017 Silver Book being adopted most frequently. 

Structure and Contractual duties

EPC contracts typically allocate substantial risk to the Contractor by way of a fixed completion date and contract price, with limited ability to be varied over the course of construction. Standard form agreements tend to be appropriate as a starting point, with parties finding it necessary to amend the terms of the contract to appropriately allocate project specific risks. The EPC contract is drafted alongside other key project documents, such as the PPP/Concession Agreement, so that it fits with the broader contractual framework and risk management of the overall Project.

The financing of a project also determines the distribution of risk between the relevant parties. Project finance, the most conventional means of funding for major infrastructure projects, relies on the projected cash flow of the completed Project itself. Therefore, the expertise and creditworthiness of the Contractor are fundamental to a project’s bankability; lenders will want to ensure that risks are sufficiently managed so that construction completes and the Project becomes operational as planned to start generating cash flow for repayment. Conversely, with the Project Company often being a newly incorporated Special Purpose Vehicle, the EPC Contractor will require assurance that funds are available for payment of its invoices.  

Key Negotiation Points

In this section we consider the areas that are subject to most negotiation when drafting an EPC contract and how the contractual strategy may differ according to the parties’ priorities.

Design Risk

In the EPC context, the Contractor usually assumes all of the design risk. Under English law, the Contractor is obliged to exercise reasonable skill and care in performing its design obligations. This position is implied into the contract by law. The position is similar under Tanzanian law; however, the parties to the EPC contract will usually agree to enhance this standard, including a warranty that the completed works will be “fit for purpose”. Failure to meet this standard may result in contractual disputes over the adequacy and quality of the services rendered.

Time for Completion and Liquidated Damages

The parties must fix a completion date by which the works (or a section thereof) must be completed. For projects in Tanzania and East Africa, it is common for liquidated damages to be payable in the event the works are not complete by the agreed date. Liquidated damages are permitted under Tanzanian law and, unlike English law, it is also possible to impose penalties for delay.  

With money on the line, it is essential for the parties to agree a clear methodology for the certification of completion. Depending on the nature of the works, the Project Company and the lenders may require that the Project passes specified performance tests before the burden of the project risks are transferred.

Extensions of Time

Whilst EPC contracts are characterised by their fixed completion date, extensions of time can still be sought in certain circumstances, granting relief from delay liquidated damages. Relief events are heavily negotiated on projects in Tanzania and this is a common area of dispute.  For instance, Tanzania is subjected to extreme weather in the form of long dry periods followed by heavy rainfall. Relief may be granted to contractors where extreme weather affects progress, but it is essential to clearly define when the relief applies as opposed to what should have reasonably been foreseen by the Contractor. 

The parties must balance contractual certainty and timeliness from a project financing perspective, against the risk of termination and cost consequences if a contractor is simply unable to complete the works by the agreed date.

Contract Pricing

The majority of EPC contracts for large-scale projects in Tanzania are priced on a lump-sum basis. The Contractor will want to include a provision which operates a price mechanism so that the contract price can be varied if deemed necessary. Similarly, the Project Company may agree to a “fluctuations” provision or advance payment, recognising that a fixed price is not always appropriate for long-term, complex infrastructure projects. 

Performance Security

It is common for parties to seek protection against non-performance of the other parties, by way of bonds or guarantees. Performance bonds are often used in construction projects in Tanzania and are heavily negotiated. In particular, parties will need to determine whether they are drafted either as conditional or on-demand. Parties should be mindful of complying with the foreign exchange regulations and requirements of the Bank of Tanzania when negotiating financial instruments in connection with EPC Contracts. 

Alternatively, if the Contractor is a local subsidiary of a larger business and there are concerns about its long-term solvency, a parent company guarantee can mitigate the risk of contractor default.

Termination

The right to terminate or suspend the project may be written into the contract and exercised in certain situations, including contractor or Project Company default. This is distinct from termination by law, which depends on the governing law of the contract. The Project Company may request a general right to terminate for convenience, though the contractor will aim to reduce this to a specific right to terminate in the case of named breaches. Termination of the EPC contract may also be triggered by termination of other agreements in the broader contractual framework for the project. 

In the event of termination, the Project Company will look to recover as much of its loss as possible from the contractor. Contractors will often negotiate caps on liability – another area which is heavily negotiated, although often informed by insurance coverage.

Tanzania Framework for Consents and Permits in Construction Projects

The Contractor should obtain necessary consents and permits to facilitate the design, procurement and construction of the Project. Below, we highlight a few key approvals along with their corresponding regulatory authorities. 

  Organisation Consent / Permit Commentary
1. National Environmental Management Council (NEMC) Air pollutant emission permit

If any air polluting activities will occur during the execution of the Project, then the Company will need to obtain this permit from the NEMC.

It is recommended that a consultant selected by the Project Company is appointed to determine whether an air pollutant emission permit should be obtained from the NEMC.

Noise emission licence  An application in the form set out in Part I of the Third Schedule to the Noise Regulations should be submitted for a licence to emit noise in excess of the permissible levels. 
Environmental Impact Assessment (EIA) Certificate Pursuant to part VI of the EIA, there are several conditions which the Project Company must follow before the granting of the EIA certificate.
2. Municipal Council Temporary / municipal construction permit An application for a building permit must be made to the Municipal Director of the local municipal council. The timing and costs depend on the local municipal council and can be between one (1) to six (6) months.
3. The Tanzania National Roads Agency (TANROADS) Permits to move extra weight, large loads or vehicles on main highway roads and municipal roads

Written application with payment must be made to TANROADS for the permit. 

The permit may be issued within 48 hours.

4.

Forest Manager 

Director of Forestry

Local Authority

Permit to use roads or paths in a forest reserve The Forest Regulations do not specify the process for applying for a forest permit, but it is provided that the permit will be granted in the prescribed form provided in the Twenty Second Schedule to the Forest Act and will contain conditions that the applicant must adhere to.
5. Water Board Water use permit An application for a water use permit must be made in the form and according to the procedure prescribed by the Minister responsible for water.
6. Contractors Registration Board (CRB) Project registration There is a requirement in paragraph 19A of the Contractor’s Registration Act 1997 to apply to the CRB for registration of the project.

Depending on the nature of the Project, additional permits specific to the industry may be required. For instance, when undertaking construction works in connection with a mine, all project stakeholders (including the contractor and sub-contractors) must adhere to the Mining (Local Content) Regulations 2018.

Key Risks in EPC Contracts in Tanzania

In this section we explore some common risks associated with the use of EPC contracts in Tanzania. 

  Issue Commentary
1 Governing law Tanzania has limited legislation and case law when it comes to construction contracts, meaning contracts governed by Tanzanian law can be interpreted inconsistently. We occasionally recommend choosing English law as the governing law of EPC Contracts for projects of a significant size in Tanzania.
2 Supply Chain and Changes in Costs We have recently advised on a number of disputes arising out of global supply chain issues, including rising costs and long lead times on delivery of plant and materials. Clear allocation of risk under the contract is essential to avoiding dispute.
3 Delay Many construction disputes in Tanzania centre on the Contractor’s entitlement to extensions of time. We usually include drafting amendments to clarify the notice requirements and ensure that any delay caused by the Contractor’s acts or omissions does not result in an extension of time.
4 Sub-contractor risk

A large number of the construction disputes we have advised on in Tanzania commence with subcontractor issues. We usually introduce provisions which afford the employer some degree of control over the terms subcontractors are engaged upon and a right to “step-in” to the subcontracts in the event the contractor’s engagement is terminated.

For mining projects, procurement of the Contractor and subcontractors should be conducted in accordance with the Mining (Local Content) Regulations 2018.  There are comparable local content requirements for the oil & gas sector.

5 Local Content For mining projects, the Contractor and subcontractors should be compliant with the Mining (Local Content) Regulations 2018.  There are similar local content requirements for the oil & gas sector.
6 Performance Security and Financing Some sureties in Tanzania have a poor record of paying out claims under performance bonds, even when they are clearly drafted as on-demand bonds. Special attention should be paid to the form of performance bond and the reputation and credit rating of the surety at the time of contracting.
7 Financing Construction There is a requirement to comply with foreign exchange laws in Tanzania. For example, all foreign loans with a tenure exceeding 365 days afforded to Tanzanian residents are required to be registered by the Bank of Tanzania.
8 Change in Law Allocation of risk for change in law is a key issue under any EPC contract, but particularly in Tanzania where the regulatory landscape is constantly evolving. 
9 Anti-bribery and corruption For many international stakeholders, it is necessary to add robust anti-corruption provisions to match their policies and extra-jurisdictional legislation applicable to their business.
10 Dispute Resolution Thought should be given to the employer’s preference for the administration of disputes. The FIDIC Silver Book provides for a Dispute Adjudication / Avoidance Board, which can provide a useful mechanism for providing interim decisions on disputes. It is reasonably and commonly adopted on projects in Tanzania, but some find it adds unnecessary cost and administration. Please note that most construction projects are chosen to be resolved by arbitration. However, there is a process regarding the enforceability of foreign judgements.

Please contact Peter Kasanda should you have any questions. 

End

Stay up to date with Clyde & Co

Sign up to receive email updates straight to your inbox!

Tanzania Knowledge Hub

Find out more